Question: Suppose you are deciding on whether to crash a projects activities and you have the following information: 1. Construct the projects network. What is the
Suppose you are deciding on whether to crash a projects activities and you have the following information:


1. Construct the projects network. What is the projects duration? What activities have slack time? What is the critical path?
2. Identify the sequencing of the activities to be crashed in the first four steps. Which critical activities should be crashed first? Why?
3. After four iterations involving crashing project activities, what has the critical path shrunk to?
4. Assume that a project penalty clause kicks in after 19 weeks. The penalty charged is $5,000 per week after 19 weeks. How would this information affect your decision to crash the project?
Duration Activity Predecessors B 5 2 D 6. 8. E,F 4+ 3. Normal Crashed Cost Extra Cost Activity (in U.S. dollars) Duration (in U.S. dollars) Duration 5,000 4 weeks 4,000 3 weeks 10,000 5 weeks 3,000 4 weeks 3,500 2 weeks 5,500 1 week D* 4,500 6 weeks 4,000 4 weeks E* 1,500 3 weeks 2,500 2 weeks 7,500 8 weeks 5,000 7 weeks G* 3.000 7 weeks 2.500 6 weeks
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
1 The project duration is 25 weeks Activities C and F have 4 weeks of slack time The critical path i... View full answer
Get step-by-step solutions from verified subject matter experts
