You are calculating the estimated time to completion for a project of 12 months duration and a
Question:
You are calculating the estimated time to completion for a project of 12 months’ duration and a budgeted cost of $500,000. Assuming the following information, calculate the Schedule Performance Index and the estimated time to completion (figures are in thousands).
Transcribed Image Text:
Schedule Variances Planned Value (PV) Earned Value (EV) Schedule Performance Index Estimated Time to Completion 65 58
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (QA)
Answered By
Asim farooq
I have done MS finance and expertise in the field of Accounting, finance, cost accounting, security analysis and portfolio management and management, MS office is at my fingertips, I want my client to take advantage of my practical knowledge. I have been mentoring my client on a freelancer website from last two years, Currently I am working in Telecom company as a financial analyst and before that working as an accountant with Pepsi for one year. I also join a nonprofit organization as a finance assistant to my job duties are making payment to client after tax calculation, I have started my professional career from teaching I was teaching to a master's level student for two years in the evening.
My Expert Service
Financial accounting, Financial management, Cost accounting, Human resource management, Business communication and report writing. Financial accounting : • Journal entries • Financial statements including balance sheet, Profit & Loss account, Cash flow statement • Adjustment entries • Ratio analysis • Accounting concepts • Single entry accounting • Double entry accounting • Bills of exchange • Bank reconciliation statements Cost accounting : • Budgeting • Job order costing • Process costing • Cost of goods sold Financial management : • Capital budgeting • Net Present Value (NPV) • Internal Rate of Return (IRR) • Payback period • Discounted cash flows • Financial analysis • Capital assets pricing model • Simple interest, Compound interest & annuities
4.40+
65+ Reviews
86+ Question Solved
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted:
Students also viewed these Business questions
-
You are calculating the estimated time to completion for a project of 15 months duration and a budgeted cost of $350,000. Assuming the following information, calculate the Schedule Performance Index...
-
Suppose, for Problem 13.20, that your PV was 70 and your EV was 95. Recalculate the SPI and estimated time to completion for the project with this new data. Problem 13.20 You are calculating the...
-
Which market segments are the most favorable for Hyundai card? Does the company do an effective job of targeting and reaching those segments? If so, How? If not, why not?
-
On December 30, Billy's Boat Yard (BBY) had $90,000 of cash, $20,000 of liabilities, $30,000 of common stock, and $40,000 of unrestricted retained earnings. On December 31, BBY appropriated retained...
-
In the probit regression given in the following table show that the intercept is equal to μ x /Ï x and the slope is equal to 1/Ï x , where μ x and Ï x are...
-
List any four differences between the horizontal milling machine and vertical milling machine.
-
Gable Industries manufactures a popular interactive stuffed animal for children that requires two computer chips inside each toy. Gable Industries pays $3 for each computer chip. To help guard...
-
Damon Associates reported the following transactions during September 2017: Sept. 8 Sold $3,000 of merchandise to Bruce Company for cash. The cost of the merchandise was $1,250 10 Owner invested...
-
Consider the following project information. The total budget is $36,000 and is expected to last six months. After four months, you have calculated the following information about the project: PV =...
-
Using the data from Problem 13.18, calculate the following values: Problem 13.18 Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual...
-
Actuary and trustee reports indicate the following changes in the PBO and plan assets of Lakeside Cable during 2011: Required: 1. Determine Lakeside's pension expense for 2011 and prepare the...
-
Kenneth's small business can produce up to 1,100 units. He looks at his profit information from the past year and notes the following: sales of $7,200, variable cost per unit of $4, fixed costs of...
-
Taylor Electronics makes and sells computers and other electronic devices. The budgeted sales are $586800, the budgeted variable costs are $184300, and the budgeted total fixed cost is $230600. What...
-
George and Wanda received $30,200 of Social Security benefits this year ($12,000 for George; $18,200 for Wanda). They also received $5,000 of interest from jointly owned City of Ranburne Bonds and...
-
Mr. John Estes oversees the distribution of Tastee Snacks products from the plant warehouse to its two distribution centers in the United States. The plant warehouse currently has 47,000 units | of...
-
The materials used by Hibiscus Company's Division A are currently purchased from an outside supplier at $55 per unit. Division B is able to supply Division A with 14,700 units at a variable cost of...
-
In Prob. 3.21, determine the perpendicular distance from point C to portion AD of the line ABAD. Problem 3.21: A small boat hangs from two davits, one of which is shown in the figure. The tension in...
-
6. (Potential Energy and Conservation of Energy) What should be the spring constant k of a spring designed to bring a 1200-kg car to rest from a speed of 95 km/h so that the occupants undergo a...
-
Most project managers are motivated by which level of Maslow's hierarchy of human needs? A. Safety B. Socialization C. Self-esteem D. Self-actualization
-
A project manager with a history of success in meeting deliverables and in working with team members would most likely possess a great deal of: A. Reward power B. Legitimate power C. Expert power D....
-
If a project manager possesses penalty (or coercive) power, he or she most likely also possesses: A. Reward power B. Legitimate power C. Expert power D. Referent power
-
1. There is an interesting optical effect you have likely noticed while driving along a flat stretch of road on a sunny day. A small, distant dip in the road appears to be filled with water. You may...
-
A helicopter with mass 2.85 x 104 kg has a position given by (t) = (0.020) + (2.2t) - (0.060t) m. Find the net force on the helicopter at t = 3.1 s. Fnet 'net = 2+ 3+ k kN
-
1. [15 marks total] Consider a mass of air in the atmosphere (a "cold front"), consisting of a rectangular prism 100. km x 100. km at its base and 1.00 km high (see the sketch below, which is not to...
Study smarter with the SolutionInn App