You manage a project with 10 activities. Activities A 1 , A 3 , A 5 ,
Question:
You manage a project with 10 activities. Activities A1, A3, A5, and A9 form the critical path. Because you have a large budget for the project, you consider crashing activity A2, which has the potential to shorten the time of A2 by three days. What do you think about this opportunity?
a. It is a good idea because it will reduce the project duration by three days.
b. It is a bad idea because A2 is not on the critical path.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 58% (17 reviews)
b It is a b...View the full answer
Answered By
Jonas Araujo
I have recently received the degree of PhD. In Physics by the Universidade Federal do Maranhão after spending a term in Durham University, as I have been awarded a scholarship from a Brazilian mobility program. During my PhD. I have performed research mainly in Theoretical Physics and published works in distinguished Journals (check my ORCID: https://orcid.org/0000-0002-4324-1184).
During my BSc. I have been awarded a scholarship to study for a year in the University of Evansville, where I have worked in detection-analysis of photon correlations in the the Photonics Laboratory. There I was a tutor in Electromagnetism, Classical Mechanics and Calculus for most of that year (2012).
I am very dedicated, honest and a fast learner, but most of all, I value a job well done.
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Operations Management
ISBN: 9781260547610
2nd International Edition
Authors: Gerard Cachon, Christian Terwiesch
Question Posted:
Students also viewed these Business questions
-
A CPM/PERT project network has probabilistic activity times (x) as shown on each branch of the network; for example, activity 13 has a .40 probability that it will be completed in 6 weeks and a .60...
-
Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In addition, you have asked your team to...
-
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities...
-
The following MINITAB output exhibits the cumulative distribution function curves of three lognormal distributions. Their mean and variance, respectively, are (1, .5), (1, 1), and (1, 2). Compare the...
-
In Exercises 1 and 2, give the vector equation of the plane passing through P, Q, and R. 1. P = (1, 1, 1), Q = (4, 0, 2), R = (0, 1, - 1) 2. P = (1, 1, 0), Q = (1, 0, 1), R = (0, 1, 1)
-
On June 3 0 , 2 0 0 9 , Martinez Company issued 1 2 % bonds with a par value of $ 7 5 0 , 0 0 0 due in 2 0 years. They were issued at 9 8 and were callable at 1 0 4 at any date after June 3 0 , 2 0 1...
-
Explain parameters and return values in the framework of messages. Provide examples.
-
Comparative statement of financial position accounts of Jensen Limited, which follows IFRS, appear below: Data from Jensen's 2017 income statement follow: Additional information: 1. Equipment that...
-
Explain the difference between traditional and enterprise risk management. Explain why enterprise risk management is a more effective approach for today's organizations. Explain key drivers of...
-
In December 2011, American Greetings closed at $12.51 a share. This was the lowest for the company in the previous 36 months. This has become a concern for management due to the concerning decline in...
-
Consider two projects that have the same activities and the same dependencies. In the first project, the activity times are expected outcomes. The actual times will vary. In the second project, the...
-
A project manager is concerned about rework, specifically about having to iterate on two activities that are on the critical path. A consultant tells the project manager not to worry, because the...
-
Southern California Publishing Company is trying to decide whether to revise its popular textbook Financial Psychoanalysis Made Simple. The company has estimated that the revision will cost $153,000....
-
Describe three ways of handling instruments that are dependent on interest rates when the model-building approach is used to calculate VaR. How would you handle these instruments when historical...
-
Identify another research question that Shuang needs to answer and develop some alternative search terms to research this question using a general search engine, a deep web search engine, or an...
-
Encourage students to share examples of their own paperless (or paper-bound) communication styles. How has paper use been encouraged or discouraged in the organizations and companies where they have...
-
Deep Seas Submarine must implement a new engine in its submarines to meet the needs of clients who desire quieter operation. Two designs, both technologically feasible, have been created, and Deep...
-
Are there any topics on which you are already a Level 2 expert (i.e., someone who has deep knowledge about a topic)? How did you gain that expertise? What research sources or approaches would you...
-
On August 1, 2017, Iroko Corporation purchased a new machine for its assembly process. The cost of this machine was $136,400. The company estimated that the machine would have a trade-in value of...
-
1. Using the information from Problem 16-4B, prepare a statement of cash flows for Lim Garden Supplies Inc. using the direct method of presenting cash flows from operating activities. 2. How does Lim...
-
The Commonwealth Banking Corporation issues a national credit card through its various bank branches in five southeastern states. The bank credit card business is highly competitive and interest...
-
The Commonwealth Banking Corporation issues a national credit card through its various bank branches in five southeastern states. The bank credit card business is highly competitive and interest...
-
In the assembly process for automobile engines, at one stage in the process a gasket is placed between the two sections of the engine block before they are joined. If the gasket is damaged (e.g.,...
-
blem 3: Consider the soil profile below. If the effective stress at point C is 111 kPa, find the value of h. (30) e=0.61 Gs=2.66 Ground Surface 4m 5m e=0.48 Gs=2.67 A PP A
-
Q4 (40 marks). Two identical rigid foundations are given. Calculate the differential settlement ratio (8/L) after 100 days and long term after construction of the foundations. Hint: Average total...
-
An embankment is given (H = 5 m and y = 20 kN/m). Determine the vertical stress increase at points A, which is 5 m below the ground surface. Assume the embankment is constructed on the ground...
Study smarter with the SolutionInn App