Question: 23. I he new software installation project is in progress. The project manager is working with the quality department to improvr stakeholders' confidence that the
23. I he new software installation project is in progress. The project manager is working with the quality department to improvr stakeholders' confidence that the project will sat isfy the quality standards.
Which of the following must they have before they star t this process?
A. Quality problems B. Quality unprovement C. Quality control measurements D. Rework