Question: The new software installation project is in progress. The project manager is working with the quality department to improve stakeholders confidence that the project will

The new software installation project is in progress. The project manager is working with the quality department to improve stakeholders’

confidence that the project will satisfy the quality standards. Which of the following must they have before they start this process?

A. Quality problems B. Quality improvement C. * Quality control measurements D. Rework