Question: Construct a network diagram based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters. Calculate the
Construct a network diagram based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters. Calculate the project duration?
- Activities A, B, C start the project.
- Activities D and E can start when Activity A is completed.
- Activity F depends on Activities A and B.
- Activity G is preceded by Activities B and C
- Activity H follows Activities D and E.
- Activity I is preceded by Activity E.
- The predecessors to Activity J are Activities F and G.
- Activity K cannot begin until Activities H, I and J are finished.