Question: The critical path method (CPM) calculates the theoretical early start and finish dates; and late start and finish dates. The difference between the late and
The critical path method (CPM) calculates the theoretical early start and finish dates; and late start and finish dates. The difference between the late and early start of a task is called:
A. Free float B. Feeding buffer C. Danger zone D. Total float