Question: The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. If no scheduling constraints have been

The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. If no scheduling constraints have been applied to the critical activities, the critical activities will have:

Zero total float

Zero or positive total float

Positive total float

Positive or negative total float