Question: The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. If no scheduling constraints have been
The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. If no scheduling constraints have been applied to the critical activities, the critical activities will have:
Zero total float
Zero or positive total float
Positive total float
Positive or negative total float