Question: Why are activity resources generally estimated before activity durations? A. Because that is the way the PMBOK Guide sets them out. B. Because in order
Why are activity resources generally estimated before activity durations?
A. Because that is the way the PMBOK Guide sets them out.
B. Because in order to estimate activity durations, you must know what sequence they occur in.
C. Because you need to know how many resources are available to complete an activity. This will affect how fast the activity can be completed.
D. They don’t—it’s better to estimate activity durations first, then estimate activity resources.