Question: Why are activity resources generally estimated before activity durations? A. Because that is the way the PMBOK Guide sets them out. B. Because in order

Why are activity resources generally estimated before activity durations?

A. Because that is the way the PMBOK Guide sets them out.

B. Because in order to estimate activity durations, you must know what sequence they occur in.

C. Because you need to know how many resources are available to complete an activity. This will affect how fast the activity can be completed.

D. They don’t—it’s better to estimate activity durations first, then estimate activity resources.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!