You're managing a project using the earned value for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the schedule performance index (SPI) for the project?
a.0.67
b.0.75
c.2
d.0.5