Question:

In the Web site development project network, shown in the following figure, the number alongside each activity designates the activity duration (TE) in weeks.

In the Web site development project network, shown in the

Determine:
(a) The ES and LS for each activity.
(b) The earliest time that the website can be completed.
(c) The slack on all activities.
(d) The critical activities.
(e) The criticalpath.