Question: Given the following information regarding a project concerning an initial public offering (IPO), (a) Draw the network. (b) What is the critical path? (c) When
Given the following information regarding a project concerning an initial public offering (IPO),
.png)
(a) Draw the network.
(b) What is the critical path?
(c) When will the offering be available (completion of the project)?
(d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extraweeks?
Preceding TE (weeks) Activities Activity a: Check feasibility b: Determine funding none none Preceding Activity TE (weeks) Activities c: Find possible banks d: Select two possibles e: Interview two banks f: Analyze funding costs 4 4 g: What chance of success? 2 c, e h: Sign contract
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
a b The critical path is B F H c Week 9 d If activity E require... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
84-B-M-L-P-M (461).docx
120 KBs Word File