Question: Consider the following network for conducting a 2-week (10 working days) computer training class: a. Construct a schedule showing: ESs for all activities LSs for
Consider the following network for conducting a 2-week
(10 working days) computer training class:

a. Construct a schedule showing:
ESs for all activities LSs for all activities Slacks for all activities Critical path
b. Given the following

1. Find the crash cost per day.
2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing.
3. Find the new cost.
A 7 2 C 6 3 B 3 D 3 4 E 5 2