Question: Problem 4 : Given the following information, answer the questions about this project: a . Draw the network as a Gantt chart. b . What
Problem :
Given the following information, answer the questions about this project:
a Draw the network as a Gantt chart.
b What is the critical path? Which activities have slack time?
c What would happen if activities B and D each took extra days to complete instead of the expected duration? How would the critical path change?
tableActivityExpected Duration,PredecessorsA days,B days,AC days,AD days,BE days,BF days,CG days,D FH days,E GI day,H