Question: Problem 4 : Given the following information, answer the questions about this project: a . Draw the network as a Gantt chart. b . What

Problem 4:
Given the following information, answer the questions about this project:
a. Draw the network as a Gantt chart.
b. What is the critical path? Which activities have slack time?
c. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?
\table[[Activity,Expected Duration,Predecessors],[A,4 days,-],[B,9 days,A],[C,11 days,A],[D,5 days,B],[E,3 days,B],[F,7 days,C],[G,3 days,D. F],[H,2 days,E. G],[I,1 day,H]]
 Problem 4: Given the following information, answer the questions about this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!