Question: If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is: A. Ahead of schedule and under budget B. Ahead of schedule
If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is:
A. Ahead of schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and over budget
D. Behind schedule and under budget
Step by Step Solution
3.34 Rating (157 Votes )
There are 3 Steps involved in it
B Ahead ... View full answer
Get step-by-step solutions from verified subject matter experts
