Question: If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is A. Ahead of Schedule and under budget B. Behind Schedule and
If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is A. Ahead of Schedule and under budget B. Behind Schedule and under budget C. * Ahead of Schedule and over budget D. Behind Schedule and over budget