Question: In a multiple-project environment, the drum resource carries a certain status, since work performed by other resources (and the needs of other resources) are subordinated
In a multiple-project environment, the drum resource carries a certain “status,” since work performed by other resources (and the needs of other resources) are subordinated to it. In one company, management placed a flag at a work center to indicate that it was the drum resource. An improvement (TOC step 4) removed this work center as the constraint, and the flag was moved elsewhere to the new constraint. People working in the original center were disappointed and protested. How do you suggest management should handle this problem?
Step by Step Solution
3.35 Rating (155 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts