One of your contractors sends you an email request to use high quality raw materials in your project, stating that this will be value-added and improve quality. What should the project manager do first?
A. Change the scope baseline.
B. Ask the contractor to put forth a change request.
C. Ask your sponsor for his or her opinion.
D. Change the WBS.