The most common constraint or relationship in a precedence network is: A. Start-to-start B. Start-to-finish C. Finish-to-start
Question:
The most common “constraint” or relationship in a precedence network is:
A. Start-to-start
B. Start-to-finish
C. Finish-to-start
D. Finish-to-finish