ActivityDescriptionDurationPredecessor
1Define scope6None
2Define customer problems31
3Define data records and relationships51
4Mass storage requirements52,3
5Consultant needs analysis102,3
6Prepare installation network34,5
7Estimate costs and budget24,5
8Design section 'point' system14,5
9Write request proposal54,5
10Compile vendor list34,5
11Prepare mgmt. control system56,7
12Prepare comparison report59,10
13Compare system 'philosophies'38,12
14Compare total installation28,12
15Compare cost of support38,12
16Compare customer satisfaction level108,12
17Assign philosophies points113
18Assign installation cost114
19Assign support cost115
20Assign customer satisfaction points116
21Select best system1$11,17,18,19,20$
22Order system121




The project team has requested that you create a network for the project and determine if the project can be completed in 45 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Understanding the Problem We are given a list of activities with 1 Durations in weeks 2 Predecessors tasks that must be finished before the current on... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!