Question: The optical disk project team has started gathering the information necessary to develop the project network predecessor activities and activity times in weeks. The results

The optical disk project team has started gathering the information necessary to develop the project networkpredecessor activities and activity times in weeks. The results of their meeting are found in the following table.
Activity
Description
Duration
Predecessor
1
Define scope
6
None
2
Define customer problems
3
1
3
Define data records and relationships
5
1
4
Mass storage requirements
5
2,3
5
Consultant needs analysis
10
2,3
6
Prepare installation network
3
4,5
7
Estimate costs and budget
2
4,5
8
Design section point system
1
4,5
9
Write request proposal
5
4,5
10
Compile vendor list
3
4,5
11
Prepare mgmt. control system
5
6,7
12
Prepare comparison report
5
9,10
13
Compare system philosophies
3
8,12
14
Compare total installation
2
8,12
15
Compare cost of support
3
8,12
16
Compare customer satisfaction level
10
8,12
17
Assign philosophies points
1
13
18
Assign installation cost
1
14
19
Assign support cost
1
15
20
Assign customer satisfaction points
1
16
21
Select best system
1
11,17,18,19,20
22
Order system

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!