Question: The project manager and the functional manager at the pharmaceutical company are having a discussion about the project to create a system to produce antibiotic
The project manager and the functional manager at the pharmaceutical company are having a discussion about the project to create a system to produce antibiotic and intravenous injection vials. The functional manager continually brings the discussion back to the costs of running the system and the length of time the system will be viable. Of the following, what best describes the functional manager’s primary focus?
a. Project management life cycle
b. Product life cycle
c. Program management life cycle
d. Project life cycle