Question: A project manager has estimated all the activities durations and is about to move on to develop the project schedule. What has he forgotten to
A project manager has estimated all the activities’ durations and is about to move on to develop the project schedule. What has he forgotten to do?
A. Sequence activities.
B. Estimate resource requirements.
C. Define communication requirements.
D. Estimate a contingency reserve.