Question: Changes are evident in all projects. Ideally, projects should have a structured Change Management Plan. When will you develop the Change Management Plan? A. During

Changes are evident in all projects. Ideally, projects should have a structured Change Management Plan.

When will you develop the Change Management Plan?

A. During the Perform Integrated Change Control process B. During the Monitor and Control Project Work process C. Along with Develop Project Charter process D. As a part of Develop Project Management Plan process