Question: During the . . . . . . . . . . . . . . . . . . . . . . Phase,

During the . . . . . . . . . . . . . . . . . . . . . . Phase, the Project Owner identifies and analyzes the Business Requirements; reviews the Organization’s current Operations;

conducts a High-Level Benefits Analysis; conducts a High-Level Budgeting;

identifies the Stakeholders and their Expectations; develops an RFP; and shares the RFP with the Service-Providers.

A) Initiation B) Planning C) Execution D) Monitoring and Control E) Closure ANSWER: A