Question: Given: AC = 100 BAC = 300 EV = 90 Assuming that the variations that have occurred so far in the project will not occur

Given:

AC = 100 BAC = 300 EV = 90 Assuming that the variations that have occurred so far in the project will not occur in the future, the EAC is:

A. 290 B. 310 C. 110 D. 400