Question: Lora Nirvana is the project manager for the Sequence the DNA of a Buffalo (SDB) project. Match each item in the first column of the

Lora Nirvana is the project manager for the Sequence the DNA of a Buffalo (SDB) project.

Match each item in the first column of the following table to the correct item in the second column..

Output of the Develop Schedule Process A. Schedule data B. Project document

Output of the Develop Schedule Process A. Schedule data B. Project document updates C. Schedule D. Schedule baseline Description 1. A bar chart that includes all the activities of the project and also includes milestones. Lora points to this bar chart for the project sponsor to show where they are in the execution of the project. 2. A bar chart hanging on the calendar that has never changed once it was approved. Lora compares the current bar chart with this bar chart to show the progress. 3. On a bar chart, Lora points to the dates when she will have the DNA sample isolated and purified, when she will get the DNA sample run through the genetic analyzer, when she will receive the results from the analyzer, and when the results will be pub- lished on the Internet. 4. After realizing that their chosen vendor has a track record of sending the DNA analysis kits late, Lora writes something into the risk register.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!