Question: The Change Control Board has approved adding two resources to a software development project. The project manager promptly updates the approval status in the change

The Change Control Board has approved adding two resources to a software development project. The project manager promptly updates the approval status in the change log.

What should be the next course of action?

A. Initiate the resource onboarding process.

B. Update the Project Management Plan and the Project Documents. C. Ask the sponsor to add more funds to the Management reserve. D. Evaluate the CCB decision with the project team.