Question: The Close Project or Phase Process is to: A) Finalize all of the Project Activities such as ensuring that all Documents and Deliverables are up-to-date
The “Close Project or Phase” Process is to:
A) Finalize all of the Project Activities such as ensuring that all Documents and Deliverables are up-to-date and that all Issues are resolved; Ensure that all Costs are charged to the Project; confirming the delivery and the Formal Acceptance of Deliverables by the Customer; Measure the Stakeholders’ Satisfaction;
and Reassign Human Resources, dealing with excess Project material and reallocating the Project Facilities and Equipment.
B) Prepare the Project Reports in accordance with the Organizational Policies;
Manage Knowledge sharing and transfer; Identify Lessons Learned; and Transfer the Project Products, Solutions, and/or Services to the next Phase or to Production/Operations.
C) Collect Suggestions for improving the Organizational Policies and Procedures;
Archive the Project Information for future use by the Organization;
and Close the Project Accounts.
D) All Options above are Correct.
ANSWER: D