Question: The Close Project or Phase Process is to: A) Finalize all of the Project Activities such as ensuring that all Documents and Deliverables are up-to-date

The “Close Project or Phase” Process is to:

A) Finalize all of the Project Activities such as ensuring that all Documents and Deliverables are up-to-date and that all Issues are resolved; Ensure that all Costs are charged to the Project; confirming the delivery and the Formal Acceptance of Deliverables by the Customer; Measure the Stakeholders’ Satisfaction;

and Reassign Human Resources, dealing with excess Project material and reallocating the Project Facilities and Equipment.

B) Prepare the Project Reports in accordance with the Organizational Policies;

Manage Knowledge sharing and transfer; Identify Lessons Learned; and Transfer the Project Products, Solutions, and/or Services to the next Phase or to Production/Operations.

C) Collect Suggestions for improving the Organizational Policies and Procedures;

Archive the Project Information for future use by the Organization;

and Close the Project Accounts.

D) All Options above are Correct.

ANSWER: D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!