Question: The main Inputs to the Close Project or Phase Process include the following: A) The Project Charter; and the Project Management Plan and its subsidiary
The main Inputs to the “Close Project or Phase” Process include the following:
A) The Project Charter; and the Project Management Plan and its subsidiary Plans and Project Documents.
B) The set of Accepted Deliverables, the relevant Business Documents, and the Procurement Documentation.
C) The Project Agreements along with the set of relevant Organizational Process Assets Factors.
D) All Options above are Correct.
ANSWER: D