Question: The customer has requested a scope change that can be implemented with no impact on the project schedule. You are also aware that implementing such
The customer has requested a scope change that can be implemented with no impact on the project schedule. You are also aware that implementing such change could greatly improve your relationship with the customer.
What should be done NEXT?
A. Implement the change and update the project management plan.
B. Analyze the impact of the change.
C. Request an approval for the change.
D. Implement the change and issue a change request to ensure traceability.