Question: The main Data Analysis Methods used during the Control Costs Process are the following: A) The Earned-Value Analysis including the Planned-for Value, Earned Value, and

The main Data Analysis Methods used during the “Control Costs” Process are the following:

A) The Earned-Value Analysis including the Planned-for Value, Earned Value, and Actual Costs.

B) The Variance Analysis including the Schedule Variance, Cost Variance, Schedule Performance Index, and Cost Performance Index.

C) The Trend Analysis including Charts and Forecasting; and the Reserve Analysis.

D) All Options above are Correct.

ANSWER: D