Question: The main Inputs to the Create Prioritized Product Backlog Process include the following: A) Inputs from the Scrum Master, the Scrum Team, and the Stakeholders.

The main Inputs to the “Create Prioritized Product Backlog” Process include the following:

A) Inputs from the Scrum Master, the Scrum Team, and the Stakeholders.

B) Epics, but not Persona.

C) The Project Vision Statement, the Program Product Backlog, the Business Requirements, the list of approved CHANGE-Requests, the list of identified Risks.

D) All Options above are Correct.

ANSWER: C