Question: The main Inputs to the Acquire Resources Process include the following: A) The Project Management Plan along with its subsidiary Plans, which are the Resource
The main Inputs to the “Acquire Resources” Process include the following:
A) The Project Management Plan along with its subsidiary Plans, which are the Resource Management Plan, and the Cost Estimates; and a set of relevant Enterprise Environmental Factors that includes the Resources Availabilities, Locations, Skills, and experience Levels; the Organizational Structure; and the Market Place.
B) The Project Management Plan along with its subsidiary Project Documents, which are the Project Schedule, Resource Calendar, Resource Requirements, and Stakeholder Register; and a set of relevant Organizational Process Assets that includes the Staffing Policies and Procedures.
C) Both Options above are Correct.
D) All Options above are Incorrect.
ANSWER: C