Question: The main Inputs to the Estimate Costs Process include the following: A) The Project Charter along with the Project Management Plan and some of its
The main Inputs to the “Estimate Costs” Process include the following:
A) The Project Charter along with the Project Management Plan and some of its subsidiaries.
B) A set of relevant Enterprise Environmental Factors and a set of relevant Organizational Process assets.
C) The Cost Management Plan, the Quality Management Plan, the Project Scope Statement, the Project Work Breakdown Structure. The WBS Directory, the Lessons Learned Register, the Project Schedule, the Resource Requirements, and the Risk Register.
D) All Options above are Correct.
ANSWER: D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
