Question: The main Inputs to the Implement Risk Responses Process include: A) The Risk Management Plan, the Lesson Learned Register, the Risk Register, and the Risk

The main Inputs to the “Implement Risk Responses” Process include:

A) The Risk Management Plan, the Lesson Learned Register, the Risk Register, and the Risk Report.

B) The Organizational Process Asset of the Lessons Learned Repository.

C) Both Options above are Correct.

D) All Options above are Incorrect.

ANSWER: C