Question: The project management team has performed earned value analysis on its project and discovered that the project is behind schedule and over budget. The SPI

The project management team has performed earned value analysis on its project and discovered that the project is behind schedule and over budget. The SPI is 0.0.

82 and the CPI is 0.

73. The team is trying to determine how efficient it will need to be with the remaining resources on the project to complete the project on budget.

Which of the following is the team trying to calculate?

a. Cost Variance

b. Cost Performance Index

c. Estimate to Complete

d. To Complete Performance Index