Question: The project team has successfully implemented the required risk responses, which has brought the project back in good shape. The project manager asked the team
The project team has successfully implemented the required risk responses, which has brought the project back in good shape. The project manager asked the team to update all the information concerning challenges faced, which went well for implementing the risk responses into a document for future reference.
What document did the project manager try to mention in the scenario stated above?
A. Risk Register B. Risk Report C. Lessons Learned Register D. Issue Log