Question: The Work Breakdown Structure (WBS) plays a vital role in creating a scope baseline for project planning, execution, and control. The scope baseline serves as
The Work Breakdown Structure (WBS) plays a vital role in creating a scope baseline for project planning, execution, and control. The scope baseline serves as an input to many of the project processes.
Which of the following is not true?
A. The scope baseline serves as an input for quality planning. B. The scope baseline serves as an input to cost budgeting. C. The scope baseline serves as an input for risk identification. D. The scope baseline management.