Question: The project team identified a new risk after implementing an approved change request on scope change. Where should the new risk be documented? A. Change

The project team identified a new risk after implementing an approved change request on scope change.

Where should the new risk be documented?

A. Change Log B. Risk Register C. Issue Log D. Assumption Log Answer- B.