Question: Which technique are team members using when they increase the activities duration estimates to account for problems? A. Float B. Risk mitigation C. Padding D.
Which technique are team members using when they increase the activities’ duration estimates to account for problems?
A. Float B. Risk mitigation C. Padding D. Reserve analysis