Question: Your team is designing a packaging robot for a pharmaceutical production line. The product owner is an engineer, and he tells you it's a waste
Your team is designing a packaging robot for a pharmaceutical production line. The product owner is an engineer, and he tells you it's a waste of the team's time to create a risk-adjusted backlog. You reply that this tool will allow the team to: A. Maximize the expected monetary value of the key product features. B. Deliver the highest-value features while mitigating the most serious threats. C. Balance continuous improvement with progressive elaboration. D. Calculate the contingency reserve needed for all the opportunities and threats.