Question: In the Earned Value Method (EVM), what does a positive Schedule Variance (SV) indicate? A. The project is ahead of schedule B. The project is
In the Earned Value Method (EVM), what does a positive Schedule Variance (SV) indicate?
A. The project is ahead of schedule B. The project is behind schedule C. The project is within the planned schedule D. The project's schedule is indeterminable