Question: In the Critical Path Method (CPM), what is the Float of an activity? A. The maximum duration an activity can be delayed without delaying the
In the Critical Path Method (CPM), what is the Float of an activity?
A. The maximum duration an activity can be delayed without delaying the project B. The Lag time of an activity C. The Lead time of an activity D. The total number of activities in the project