Question: In exercise 14, assuming an unforeseen condition delayed the contractor by 10 days. Since the project finish deadline is very strict, the owner demanded project
In exercise 14, assuming an unforeseen condition delayed the contractor by 10 days. Since the project finish deadline is very strict, the owner demanded project acceleration so the project could be finished on time. This led to a claim by the contractor which made the budget overrun 3.8%. Calculate the project success grade. Do you believe there were any mitigating circumstances that we must take into account when calculating project success?