Question: A project schedule completion date will change if: (a) The critical path is reduced (b) The contingency is no longer available (c) No float time

A project schedule completion date will change if:

(a) The critical path is reduced

(b) The contingency is no longer available

(c) No float time is available

(d) Project resources are reduced