Question: A project schedule completion date will change if: (a) The critical path is reduced (b) The contingency is no longer available (c) No float time
A project schedule completion date will change if:
(a) The critical path is reduced
(b) The contingency is no longer available
(c) No float time is available
(d) Project resources are reduced