Question: Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider:
Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider:
(a) Crashing the schedule
(b) Performing resource leveling
(c) Conducting reverse resource allocation scheduling
(d) Utilizing the critical chain resources