Question: Based on an initial planning session, you realize that the project cannot meet the desired end date. You immediately negotiate with the manager of another
Based on an initial planning session, you realize that the project cannot meet the desired end date. You immediately negotiate with the manager of another project to transfer an experienced staff to your project and take over some activities. This technique is known as:
(a) Crashing
(b) Fast tracking
(c) Critical chain
(d) Optimization