Question: A task was scheduled to use two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign
A task was scheduled to use two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign one person to this task. At the end of two weeks, the person assigned to the task was 75% complete. What is the cost performance index?
A. 0.5 B. * 1.5 C. 1.1 D. 0.7
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
