Question: Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?
Abdullah, a project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which of the following process?
-
Sequence Activities
-
Develop Schedule
-
Estimate Activity Durations
-
Define Activities